Previously, a notice was sent out to inform you of the upcoming street work to be done by Alpha Paving in The Woods subdivision. Each Customer will be required to adhere tothe following:
No vehicles, including The Woods residents or private contractors, will be allowed to park or drive on the specified streets below during the dates noted, between 8am-5pm. Towing will be enforced. Please plan accordingly to either be gone from home between 8am-5pm, or home during these times. Residents who do need to drive during the course of this street enhancement project may want to move a car onto a nearby street that isn’t being worked on so they will have access to a vehicle. For example, while the Navidad Drive and Navidad Cove work is being completed, Residents on those streets may want to move a vehicle over to Mendocino Drive or Ravelo Ridge during the days of the Navidad street enhancement work
No home deliveries (Amazon, UPS, etc.,) will be allowed on the specified streets below during the dates noted. A flyer will be placed at the front gate and mailboxes to notify delivery services. If you expect something urgent, please must make other arrangements for home deliveries. Please reschedule contractors to accommodate the street upgrades.
Residents must turn off all irrigation systems along the specified streets below during the dates noted. Please adjust your irrigation schedule to accommodate.
Trash and recycle collection for just homes in the Red section of Maravillas Loop and Mendocino Drive has been scheduled for Saturday, June 4. Homes in theYellow and blue sections will still maintain normal Friday collection.
Replacement of speed humps, milling and replacement of the existing asphalt on Navidad Drive and Navidad Cove is scheduled for May 25th and May 26th, from 8am – 5pm daily. (Weather permitting)
The crack sealing and seal coating of Mendocino Drive, Maravillas Loop and Maravillas Cove is scheduled for June 1st through June 3rd, from 8am – 5pm daily. (Weather permitting) Please see map on the next page which describes when each section of Mendocino and Maravillas will be completed.
Your participation and cooperation will help this project be completed in a timely and thorough manner. For more information, please contact the Gary Engineering, Inc., Herb Edmonson, at 512-452-0371.